COMMISSION STAFF WORKING DOCUMENT Accompanying the document Proposal for a Council Regulation establishing a dedicated financial programme for decommissioning of nuclear facilities and management of radioactive waste, and repealing Council Regulation (Euratom) No 1368/2013

Tilhører sager:

Aktører:


    1_EN_autre_document_travail_service_part1_v9.pdf

    https://www.ft.dk/samling/20181/kommissionsforslag/KOM(2018)0467/kommissionsforslag/1497327/1912530.pdf

    EN EN
    EUROPEAN
    COMMISSION
    Brussels, 13.6.2018
    SWD(2018) 343 final
    COMMISSION STAFF WORKING DOCUMENT
    Accompanying the document
    Proposal for a Council Regulation
    establishing a dedicated financial programme for decommissioning of nuclear facilities
    and management of radioactive waste, and repealing Council Regulation (Euratom) No
    1368/2013
    {COM(2018) 467 final}
    Europaudvalget 2018
    KOM (2018) 0467
    Offentligt
    1
    1. INTRODUCTION: POLITICAL AND LEGAL CONTEXT.....................................3
    1.1. Scope and context.........................................................................................................3
    1.1.1. Kozloduy programme and Bohunice programme ............................................................5
    1.1.2. JRC decommissioning and waste management programme ............................................8
    1.2. Lessons learned from previous programmes ..............................................................11
    1.2.1. Kozloduy programme and Bohunice programme ..........................................................11
    1.2.2. JRC decommissioning and waste management programme ..........................................13
    2. THE OBJECTIVES...................................................................................................15
    2.1. Challenges for the programmes of the next MFF .......................................................15
    2.1.1. Kozloduy programme (BG) and Bohunice programme (SK) ........................................15
    2.1.2. JRC decommissioning and waste management programme ..........................................16
    2.2. Objectives of the programmes of the next MFF.........................................................19
    2.2.1. General objectives..........................................................................................................19
    2.2.2. Objectives of the Kozloduy and Bohunice programmes................................................19
    2.2.3. Objectives of the JRC decommissioning and waste management programme ..............20
    2.2.4. Common specific objectives ..........................................................................................21
    3. PROGRAMME STRUCTURE AND PRIORITIES.................................................23
    3.1. Kozloduy programme and Bohunice programme.......................................................23
    3.2. JRC decommissioning and waste management programme.......................................24
    4. DELIVERY MECHANISMS OF THE INTENDED FUNDING ............................25
    4.1. Kozloduy programme (BG) and Bohunice programme (SK).....................................25
    4.1.1. Policy option 1 - Discontinuation of the programmes....................................................26
    4.1.2. Policy option 2 - Programmes under cohesion policy....................................................26
    4.1.3. Policy option 3 - Programmes as dedicated spending programme.................................28
    4.1.4. Policy options benchmark..............................................................................................29
    4.2. JRC decommissioning and waste management programme.......................................29
    5. HOW WILL PERFORMANCE BE MONITORED AND EVALUATED? ............30
    5.1. Kozloduy programme and Bohunice programme.......................................................30
    5.1.1. Programming, monitoring and control system...............................................................30
    5.1.2. Performance indicators...................................................................................................31
    5.1.3. Preliminary evaluation criteria.......................................................................................32
    5.2. JRC decommissioning and waste management programme.......................................32
    5.2.1. Programming, monitoring and control system...............................................................32
    5.2.2. Performance indicators...................................................................................................33
    ANNEX 1: PROCEDURAL INFORMATION ................................................................34
    ANNEX 2: FUNDING......................................................................................................35
    2
    Glossary
    Term or acronym Meaning or definition
    BG Republic of Bulgaria
    D&WMP JRC decommissioning and waste management programme
    EBRD European Bank for Reconstruction and Development
    ECA European Court of Auditors
    ESIF European Structural and Investment Funds
    ESSOR Essai Orgel research reactor at JRC Ispra
    EVM Earned Value Management
    HFR High-flux research reactor at JRC Petten
    IAS Internal Audit Service
    ISPRA-1 Research reactor at JRC Ispra
    ISSG Inter-service Steering Group
    JRC Joint Research Centre
    KPI Key Performance Indicator
    MFF Multi-annual Financial Framework
    NDAP Nuclear Decommissioning Assistance Programmes,
    whereby the EU provides financial support to Lithuania to shut
    down and decommission two reactors at the Ignalina NPP, to
    Bulgaria to shut down and decommission four reactors at the
    Kozloduy NPP, and to Slovakia to shut down and decommission
    two reactors at the Bohunice V1 NPP.
    NPP Nuclear Power Plant
    'Radioactive Waste' directive Council Directive 2011/70/Euratom of 19 July 2011 establishing a
    Community framework for the responsible and safe management of
    spent fuel and radioactive waste
    SERAW State Enterprise Radioactive Waste (BG)
    SIEA Slovak Innovation and Energy Agency
    SK Slovak Republic
    VVER Water-Water Energetic Reactor is a series of pressurised water
    reactor designs originally developed in the Soviet Union.
    3
    1. INTRODUCTION: POLITICAL AND LEGAL CONTEXT
    1.1. Scope and context
    The present ex-ante evaluation relates to the funding programme for financial assistance for
    "Decommissioning of Nuclear Facilities and Management of Radioactive Waste", (the
    'programme') that addresses the decommissioning of nuclear facilities and the management of the
    arising waste under a common instrument to optimise synergies and knowledge sharing in order
    to secure meeting of relevant obligations.
    This ex-ante evaluation identify the following needs on a current basis:
     The Kozloduy nuclear power plant units 1-4 (Kozloduy, Bulgaria) and the Bohunice V1
    nuclear power plant (Jaslovské Bohunice, Slovakia) consist of six pressurized water
    reactors originally developed in the Soviet Union (VVER 440). The decommissioning of
    these plants contributes towards increased nuclear safety in the region and in the EU as a
    whole.
     The Commission's Joint Research Centre (JRC) owns nuclear research installations in
    four sites: JRC-Geel in Belgium, JRC-Karlsruhe in Germany, JRC-Ispra in Italy and
    JRC-Petten in the Netherlands. Some of these installations are still in use today while
    others have been stopped. The JRC is responsible for the decommissioning of these
    installations and for the safe management from generation to disposal of the resulting
    spent fuel and radioactive waste.
    Figure 1 – Decommissioning sites.
    4
    Given this making, the programme is naturally subdivided into:
    (i) the two programmes providing financial support to Bulgaria and Slovakia to safely
    decommission six nuclear reactors at the Kozloduy nuclear power plant units1-4 and
    the Bohunice V1 nuclear power plant (respectively the 'Kozloduy programme' and the
    'Bohunice programme'); and
    (ii) the programme of Joint Research Centre (JRC), implementing safely the
    decommissioning process and the management of the resulting radioactive waste of the
    Commission's own nuclear installations at the JRC sites (the 'JRC decommissioning and
    waste management programme', D&WMP).
    This ex-ante evaluation is carried out in preparation of the next MFF and it is based on the
    lessons learnt and progress achieved so far.
    5
    1.1.1. Kozloduy programme and Bohunice programme
    The Kozloduy and Bohunice programmes originated in the context of the negotiations for
    accession to the EU of Bulgaria and Slovakia, which took the commitment to close and
    subsequently decommission their old Soviet-designed nuclear reactors by a commonly agreed
    date. The closure commitment of the two Member States as well as the commitment of the EU to
    provide financial support was foreseen in the corresponding Accession Treaties1,2
    (Slovakia
    acceded in 2004; Bulgaria in 2007). The two Member States and the EU have fulfilled their
    respective Accession Treaty commitment.
    On the basis of Article 203 of the Euratom Treaty3
    and to ensure continuity of safety related
    measures, the EU provided financial assistance4,5
    to the decommissioning of Bohunice V1 NPP
    beyond the timeframe that was stipulated in Slovakia's Accession Treaty6
    . Similarly, following
    the period covered by Bulgaria's Accession Treaty7
    the EU continued providing financial
    assistance5,8
    for the safe decommissioning of the Kozloduy NPP Units 1-4.
    The programmes have been subject to extensive audits in the first part of the current MFF: an
    internal audit conducted by the Internal Audit Service (IAS) that resulted in three
    recommendations9
    , all implemented to date; a performance audit of the European Court of
    Auditors that issued a special report10
    resulting in eight recommendations, either fulfilled or
    under implementation according to the established plan. In particular, the recommendation no 5
    issued by the European Court of Auditors (ECA) calls for discontinuation of the programmes
    after 2020 or transfer under other instruments (such as the European Structural Investment Funds,
    ESIF). Therefore, as per the reply provided by the Commission11
    , an assessment of policy options
    is presented in this ex-ante evaluation in order to examine if the existing instruments for support
    to Bulgaria and Slovakia should be:
    1
    OJ L236, 23.9.2003, p. 33 and p. 954
    2
    OJ L157, 21.6.2005, p.11 and p. 38
    3
    "If action by the Community should prove necessary to attain one of the objectives of the Community and this
    Treaty has not provided the necessary powers, the Council shall, acting unanimously on a proposal from the
    Commission and after consulting the European Parliament, take the appropriate measures." (Article 203 Treaty
    establishing the European Atomic Energy Community)
    4
    Council Regulation (Euratom) No 549/2007 of 14 May 2007 on the implementation of Protocol No 9 on Unit 1
    and Unit 2 of the Bohunice V1 nuclear power plant in Slovakia to the Act concerning the conditions of accession
    to the European Union of the Czech Republic, Estonia, Cyprus, Latvia, Lithuania, Hungary, Malta, Poland,
    Slovenia and Slovakia (OJ L 131, 23.5.2007, p. 1)
    5
    Council Regulation (Euratom) No 1368/2013 of 13 December 2013 on Union support for the nuclear
    decommissioning assistance programmes in Bulgaria and Slovakia (OJ L 346, 20.12.2013, p. 1)
    6
    Article 2.1 "During the period 2004-2006, the Community shall provide Slovakia with financial assistance in
    support of its efforts to decommission and to address the consequences of the closure and decommissioning of
    Unit 1 and Unit 2 of the Bohunice V1 Nuclear Power Plant" ." (Act of accession, Protocol No 9 - OJ L954,
    23.9.2003)
    7
    Article 30.2 "During the period 2007-2009, the Community shall provide Bulgaria with financial assistance in
    support of its efforts to decommission and to address the consequences of the closure and decommissioning of
    Units 1 to 4 of the Kozloduy Nuclear Power Plant." (2005 Act of accession, Protocol Concerning the conditions
    and arrangements for admission of the republic of Bulgaria and Romania to the European Union (OJ L157,
    21.6.2005))
    8
    Regulation (Euratom) No 647/2010 of the Council of 13 July 2010 on financial assistance of the Union with
    respect to the decommissioning of Units 1 to 4 of the Kozloduy Nuclear Power Plant in Bulgaria (Kozloduy
    Programme) (OJ L 189, 22.7.2010, p.9)
    9
    The recommendations concerned the assessment of ex-ante conditionalities, the control strategy, and the co-
    financing.
    10
    ECA Special Report 22/2016 - EU nuclear decommissioning assistance programmes in Lithuania, Bulgaria and
    Slovakia: some progress made since 2011, but critical challenges ahead.
    11
    The Commission's reply to recommendation 5 ("Discontinue dedicated funding programmes for nuclear
    decommissioning in Lithuania, Bulgaria and Slovakia after 2020") of the ECA Special Report 22/2016 reads:
    "The Commission will carry out an impact assessment […] with regard to proposals of new [nuclear
    decommissioning] initiatives. This impact assessment will explore whether funding should be continued and if so
    the most suitable financing mechanisms."
    6
    (i) discontinued in the next MFF, or
    (ii) merged into the Funds under cohesion policy, or
    (iii) merged in a combined programme including the decommissioning of JRC sites
    (baseline option).
    Originally and until 2013 the European Union assistance was designed to support these Member
    States both in their efforts to shut down and decommission the concerned reactors, but also to
    address the consequences of the early closure, such as enhancement of security of supply and
    energy efficiency. This has changed under the current MFF where the scope of the programmes
    was restricted to decommissioning activities only, i.e. on safety related measures. The disposal of
    spent fuel and radioactive waste in a deep geological repository was never part of the programme.
    This shift from financing a complex mix of energy and decommissioning projects towards a
    dedicated and focused effort on decommissioning programmes resulted in increased effectiveness
    and efficiency.
    More in particular, in the MFF 2014-2020 the programmes objectives have been specified as
    follows:
    Table 1: Specific objectives for MFF 2014-2020
    SPECIFIC OBJECTIVES
    Kozloduy programme
    and
    Bohunice programme
     Dismantling of large components and equipment in the reactor
    buildings;
     Dismantling in turbine halls and auxiliary buildings;
     Safely managing the decommissioning waste in accordance with
    detailed waste management plans.
    The implementation procedures12
    of the current Regulation established the baseline
    (decommissioning plans) for each decommissioning programme up to the respective end-state
    and provided concrete targets per each specific objective of the current MFF.
    The European Union financial assistance has been implemented by indirect management13
    since
    its inception. It has been made available through pillar assessed implementing bodies in the form
    of contributions:
    (i) to two International Decommissioning Support Funds14
    managed by the European Bank
    for Reconstruction and Development (EBRD) since 2001;
    (ii) to Slovak Innovation and Energy Agency (SIEA) for the Bohunice programme since
    2016, reflecting increased national ownership of the programme.
    The total financial assistance from the European Union to the two Member States for the
    decommissioning of the concerned reactors as well as for mitigating measures in the energy
    sector until the end of 2020 sums up to EUR 1 992 million. Thereof EU assistance earmarked for
    decommissioning of the six reactors until the end of 2020 sums up to EUR 1 446 million (see
    Annex 2).
    12
    Commission Implementing Decision of 7.8.2014 on the rules of application for the nuclear decommissioning
    assistance programmes for Bulgaria, Lithuania and Slovakia for the period 2014-2020 — C(2014) 5449 final
    13
    Art 60 Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council of 25 October
    2012 on the financial rules applicable to the general budget of the Union
    14
    Kozloduy International Decommissioning Assistance Fund;
    Bohunice International Decommissioning Assistance Fund.
    7
    As mentioned, for the two nuclear power plants the final decommissioning plans (baseline) were
    prepared in 2014
    15
    . These plans set out the schedules, covering a timespan longer than the current
    MFF, and the cost estimates for the decommissioning activities until the accomplishment of a
    well-established end-state. Funding provided in this MFF is fit for effective and efficient
    accomplishment of the related objectives.
    In line with the Rome Declaration16
    , the EU budget should enable a Europe that is safe and
    secure; this is a dimension where the nuclear decommissioning programmes have contributed so
    far and may further contribute. The main positive impact to be achieved by the programmes is
    indeed the progressive decrease of the level of radiological hazard for the workers, the public and
    the environment in the concerned Member States but also in the EU as a whole. Nuclear
    decommissioning and waste management are key processes of a modern, clean and circular
    economy.
    Like all existing EU instruments the programmes need to undergo the EU value added test in line
    with the reflection paper17
    on the future of EU finances. As reflected in the list of options,
    consideration is hereby given whether the programmes remain indispensable or whether there is
    scope for merging programmes or modifying them with a view to budgetary flexibility and/or
    simplification, which are other key principles underpinning the next MFF. The programmes' EU
    added value test fits into the lines and principles drawn by the Commission in its
    communication18
    on a new, modern Multi-annual Financial Framework (MFF) post-2020.
    The programmes have taken the attention of both the European Parliament and the Council of the
    European Union. Both bodies intervened specifically on the Nuclear Decommissioning
    Assistance Programmes (NDAP) after the publication of the dedicated ECA Special Report10
    .
    The European Parliament19
    underlined that nuclear safety is of prime importance, not only for the
    Member States concerned but for the population in the whole Union and its neighbourhood and
    called upon the Commission to perform a thorough assessment of the needs for continuation of
    the dedicated funding programmes for nuclear decommissioning in Bulgaria and Slovakia
    beyond 2020.
    The Council20
    also recalled that the premature closure and subsequent decommissioning of the
    Soviet-designed nuclear reactors in Bulgaria and Slovakia was one of the conditions for
    accession to the EU. It further underlined the fact that this condition entailed a significant
    financial burden based on which the EU agreed to provide financial assistance, underscored the
    need for adequate supporting actions for the decommissioning of the concerned nuclear power
    plants in the two Member States to ensure successful completion of the decommissioning
    processes whilst maintaining a high level of nuclear safety, and noted that any potential new EU
    funding beyond 2020 should include clear rules and the right incentives to pursue
    decommissioning, with regard to both financing and timing.
    15
    The definition of detailed decommissioning plans and the associated financing plans was a pre-condition (ex-ante
    conditionality) to the launch of the programme in the MFF 2014-2020. These plans describe in detail the
    decommissioning strategy, how the facilities will be safely dismantled, how radiation protection of workers and
    the public is ensured, how environmental impacts are addressed, how materials – radioactive and non-radioactive
    – are to be managed, and how the regulatory authorisation for the facilities and sites are to be terminated.
    16
    Declaration of the leaders of 27 member states and of the European Council, the European Parliament and the
    European Commission (25 March 2017)
    http://www.consilium.europa.eu/en/press/press-releases/2017/03/25/rome-declaration/pdf
    17
    Reflection Paper on the Future of EU Finances - COM(2017) 358
    18
    Communication from the Commission to the European Parliament, the European Council and the Council - A
    new, modern Multiannual Financial Framework for a European Union that delivers efficiently on its priorities
    post-2020 - COM(2018) 98 final
    19
    Committee on Budgetary Control "Report on the Court of Auditors’ special reports in the context of the 2015
    Commission discharge" (2016/2208(DEC))
    20
    Council conclusions on the ECA Special Report No 22/2016, adopted by the Council at its 3511th meeting held
    on 13 December 2016 (document n° 15534/16 ATO 68)
    8
    1.1.2. JRC decommissioning and waste management programme
    The JRC's D&WMP relates to nuclear facilities and spent fuel and radioactive waste owned by
    the Commission.
    The JRC was established under Article 8 of the Euratom Treaty:
    (1) After consulting the Scientific and Technical Committee, the Commission shall
    establish a Joint Nuclear Research Centre. This Centre shall ensure that the research
    programmes and other tasks assigned to it by the Commission are carried out. It shall
    also ensure that a uniform nuclear terminology and a standard system of measurements
    are established. It shall set up a central bureau for nuclear measurements.
    (2) The activities of the Centre may, for geographical or functional reasons, be carried
    out in separate establishments
    In application of this Article, Site agreements were signed during the period 1960-62 between the
    Community, Germany, Belgium, Italy and the Netherlands. In the two latter cases national
    nuclear installations were transferred to the Community. An infrastructure geared to nuclear
    research was put in place at the four sites. Some of these installations are still in use today while
    others have been stopped, in some instances more than 20 years ago, and have mostly become
    obsolete.
    On the basis of Article 8 of the Euratom Treaty, the JRC has to manage its historical nuclear
    liabilities and decommission its shut-down nuclear installations. To this end, a budget heading
    was created in agreement with the European Parliament and the Council. The Commission's
    objective has always been to provide sound management to clear Euratom's nuclear liabilities,
    part of which stem from the development of families of reactors at the start of the 1960s and the
    rest from research programmes on reactor safety.
    To this end and based on the 1999 Communication of the Commission "Historical Liabilities
    Resulting from Nuclear Activities carried out at the JRC under the Euratom Treaty –
    Decommissioning of obsolete Nuclear Installations and Waste Management" (COM(1999)114),
    the programme was initiated and a specific ad hoc budget line was created, in agreement with the
    European Parliament and the Council (European Parliament Resolution on Historical liabilities
    resulting from nuclear activities carried out at the JRC21
    ). Since then, the Commission reports
    regularly to the Council and European Parliament on the progress of the D&WM programme,
    thereby providing an updated budget forecast (2004, 2008, and 201322
    ).
    The aim of this ex-ante evaluation is to evaluate how the JRC could tackle best the challenges the
    D&WM programme currently faces. More specifically, there is a need for an appropriate level of
    flexibility and maximised effectiveness and efficiency. The ex-ante evaluation will also give the
    rational for the projections and estimations of the budgetary needs, and address the risks
    associated with the programme implementation.
    21
    European Parliament resolution on the communication from the Commission to the European Parliament and the
    Council on historical liabilities resulting from nuclear activities carried out at the JRC under the Euratom Treaty
    (COM(1999) 114 + C5-0214/1999 + 1999/2169(COS)) (OJ C 67, 1.3.2001, p. 167)
    22
    Communication from the Commission to the Council and the European Parliament - Decommissioning of
    nuclear installations and waste management - Nuclear liabilities arising out of the activities of the Joint Research
    Centre (JRC) carried out under the Euratom Treaty, SEC(2004)621 final
    Communication from the Commission to the Council and the European Parliament - Decommissioning of
    Nuclear Installations and Management of Radioactive Waste: Management of Nuclear Liabilities arising out of
    the Activities of the Joint Research Centre (JRC) carried out under the Euratom Treaty, COM(2008)903 final
    Communication from the Commission to the Council and the European Parliament - Decommissioning of
    Nuclear Installations and Management of Radioactive Waste: Management of Nuclear Liabilities arising out of
    the Activities of the Joint Research Centre (JRC) carried out under the Euratom Treaty, COM(2013)734 final
    9
    Scope of the D&WMP
    As nuclear operator under Italian, Dutch, German and Belgian laws, JRC is responsible in these
    four Member States for the decommissioning of these installations and for the safe management
    from generation to disposal of the resulting spent fuel and radioactive waste.
    Initially, the D&WM programme focused on the so-called "historic liabilities", mainly
    constituted by Ispra's nuclear facilities that had ceased to operate in the previous decades. This
    also included the historical waste present at the JRC sites. Currently the programme covers also
    the nuclear installations which will become obsolete in the future at all four JRC sites, including
    the management of nuclear material. The D&WM programme shall contribute to the JRC host
    Member States national programmes in their implementation of the Council Directive
    2011/70/Euratom on the responsible and safe management of spent fuel and radioactive waste. In
    line with Article 7 of the Directive, JRC has the prime responsibility for the safe management of
    the spent fuel and radioactive waste that is generated from its operations. Therefore, the costs of
    the management of these materials from generation to disposal including the disposal of spent
    fuel and radioactive waste in a final repository are included in the scope of the programme.
    To this end, JRC has re-assessed in detail its strategy, schedule and budget needs for the future.
    The revised tentative timeframe as of 2017 indicates that:
    (i) at JRC Ispra, decommissioning is ongoing and will be completed by 2038;
    (ii) at JRC Petten, the JRC-owned High-Flux Reactor (HFR) is operated by a private
    company and is today one of the major producers of some medical radioisotopes. It is
    also used in the frame of R&D (by JRC and Member States). Decommissioning will start
    under the responsibility of JRC after the shut-down of the reactor. This will certainly
    happen once a replacement reactor will be available (shutdown foreseen in 2025, when
    the new Dutch research reactor (PALLAS) is expected to be operational according to the
    Article 41 notification for new investment received by the Commission from the Dutch
    authorities);
    (iii) at JRC Karlsruhe, nuclear R&D operation will normally continue on long-term until the
    end of the site lease contract in 2059. However, three nuclear laboratory buildings will
    successively get obsolete and be decommissioned, starting in 2025;
    (iv) at JRC Geel, nuclear R&D operation will normally continue on long-term until the end of
    the site lease contract in 2060.
    In line with the reflection paper on the future of EU finances, the JRC has undergone the EU
    value added test. Having the responsibility for the safe management of its own spent fuel and
    nuclear waste in the four host Member States, the D&WM programme remains indispensable for
    the fulfilment of the Commission's obligations as licence holder23
    of these facilities. By releasing
    as soon as possible any obsolete nuclear research facilities free of radiological constraint, it
    contributes to a Europe that is safe and secure and sets a good benchmark across Europe for the
    safe and responsible management of radioactive waste and spent fuel. The timely completion of
    this process though is highly dependent on the host Member State.
    23
    JRC is owner and/or license holder for the operation of the nuclear facilities in Ispra, Karlsruhe and Geel. The
    current license holder for the operation of the nuclear facility in Petten is the private company NRG (medical
    radioisotope production), but as owner of the facility the JRC is liable for decommissioning and waste
    management.
    10
    Implementation and Financing
    As nuclear operator under Belgian, Dutch, German and Italian laws, the Commission is legally
    obliged to provide for, and maintain, adequate financial and human resources necessary to fulfil
    its obligations with respect to nuclear safety of a nuclear installation (Article 6 of Directive
    2009/71/Euratom). In addition, the Commission as licence holder23
    has the prime responsibility
    for the safety of spent fuel and radioactive waste management of the facilities and/or activities
    that fall under its responsibility (Article 7 of Directive 2011/70/Euratom).
    Therefore, the D&WM programme is implemented by direct management, under the
    responsibility of JRC; outsourced services and supplies are financed by an ad hoc budget line
    specifically created for this purpose by agreement between the Council and the European
    Parliament. However, this budget line cannot be used for administrative expenses (e.g. staff costs,
    technical experts) which represent an important part of the decommissioning process. As a result,
    the human resources necessary for the implementation of the programme (for management and
    supervision) have been so far funded through the Euratom Research and Training framework
    programme.
    The timely completion of the D&WM programme is highly dependent on the host Member State.
    Moreover, in light of the expected increase of decommissioning activities at the different sites,
    continuing financing decommissioning staff from the Euratom Research and Training framework
    programme bears the risk of penalising the overall JRC's research work programme in the future.
    Therefore, the Commission services have extensively worked with JRC to identify options to
    further improve the management and governance in implementing the programme. In the long
    term, a handing over of JRC nuclear facilities including nuclear material would present financial
    and legal benefits for JRC – it would ensure that the JRC would cease to be responsible for
    decommissioning and waste management, would no longer bear the associated costs and it would
    release JRC from its obligations as nuclear operator. Should the negotiation with host Member
    states encounter difficulties, the JRC will nevertheless ensure sufficient personnel, to carry out in
    an appropriate and safe way its decommissioning activities and fulfil its legal obligations also
    with regard to waste management.
    Since its launch in 1999, the D&WM Programme will have consumed EUR 535 million of
    operational credits by 2020. Pre-decommissioning activities have been pursued under the current
    licenses, following the granting of ad hoc authorisations by the national Safety Authorities. The
    greatest part of the budget however has been spent for maintaining the safety of the shut-down
    nuclear installations in Ispra, for building up the waste management infrastructures in Ispra, and
    for the management of JRC's nuclear material and waste (see section 2.1.2). This includes the
    mandatory payments for the ongoing construction of the German repository.
    The JRC is regularly reviewing the progress and performance of the programme using
    independent external advice (D&WM programme Expert Group, external consultants). The
    programme has made important progress and achievement since its launch. The programme is
    also audited by the EC Internal Audit Service. Following the recommendations from the last
    audit, JRC has revised the decommissioning planning and determined expected costs for each
    JRC site using a harmonised approach, based on recent international recommendations for
    estimation of decommissioning costs. The new strategy and budget forecast was reviewed by the
    D&WM Programme Expert Group and received a positive opinion in 2017. Still, significant
    uncertainties affect the timelines and the cost estimate for the different sites.
    In light of the financial uncertainties and the risk to penalise JRC's research work programme in
    the future, an instrument which fully covers the JRC D&WM programme including
    administrative costs is fundamental.
    11
    1.2. Lessons learned from previous programmes
    1.2.1. Kozloduy programme and Bohunice programme
    A mid-term evaluation of the NDAP was conducted pursuant to Article 9 of the relevant Council
    Regulation5
    , and in line with the Better Regulation guidelines. The mid-term evaluation
    considered and assessed the results and impacts, the efficiency of the use of resources and its
    Union added value. The evaluation focused on the period 2014-2017 but considered where
    relevant the previous financial framework (2007-2013).
    For the mid-term evaluation the Commission gathered relevant information and data by
    extensively involving key stakeholders (i.e. Ministries, implementing bodies, decommissioning
    operators, members of the NDAP Committee).
    Moreover, an Open Public Consultation was launched by the Commission in June 2017 for an
    extended duration of 14 weeks. The consultation received limited interest (20 responses). In
    addition to this consultation, a targeted e-survey consultation was launched in July 2017; it
    gathered an additional 17 responses (1 from Bulgaria, 4 from Lithuania and 12 from Slovakia)
    from 90 stakeholders contacted in total. The replies received were overall positive about the
    NDAP but did not provide any additional input on the programmes. These two consultations
    were complemented with targeted consultations of around 100 interviews with decommissioning
    operators and relevant stakeholders.
    The conclusions of the NDAP mid-term evaluation can be summarised as follows:
    Coherence with EU policies. The mid-term evaluation concluded that the NDAP are coherent
    with EU policies aiming at ensuring the highest level of nuclear safety. The EU support
    through the NDAP ensures that the immediate dismantling strategy in Bulgaria and Slovakia is
    steadily pursued and prevents that undue burden is transferred to future generations, while it
    partially derogates for historical reasons to the ultimate responsibility of the Member States to
    ensure adequate financial resources for nuclear decommissioning and radioactive waste
    management. The decommissioning strategy in Bulgaria was modified in 2013 in preparation for
    the current MFF: the resulting plan advanced the end date of the programme by seven years from
    2037 to 2030.
    Progress. In line with expectations set for the MFF 2014-2020, Bulgaria and Slovakia have
    progressed effectively and efficiently in the decommissioning of their reactors in line with
    the agreed baseline (decommissioning plans). There have been challenges and setbacks due to the
    programmes' complexity, but the management system has proven increasing ability to cope with
    them. Roadblocks from the previous financial framework have been removed and delays carried
    over were recovered to the extent possible.
    Safety. The analysis demonstrated also that substantially improved levels of safety are going to
    be achieved at the sites as a result of the Union funding in this MFF. Major ongoing
    developments in the field are:
     in Bulgaria the construction of the disposal facility for low level waste, the management
    of legacy waste, and decontamination and dismantling works in the reactor buildings;
     in Slovakia the finalisation of the reactor cores dismantling.
    Financial scope. The preparation and endorsement in 2014 of the respective decommissioning
    plans was a major milestone and clarified scope, schedule, and budget of the decommissioning
    programmes. Between 2014 and 2016, the Commission has analysed these baselines and
    concluded that they are based on complete and comprehensive plans, and on sound overall cost
    estimates which could be improved by considering a higher level of contingencies (max 16%). In
    2017, the cost estimate until the decommissioning end-state was confirmed for the Bohunice
    12
    programme, whereas for the Kozloduy programme the organisation responsible for
    decommissioning, State Enterprise Radioactive Waste (SERAW), has produced a draft updated
    cost estimate as part of the compulsory triannual review foreseen under the Bulgarian legislation,
    which claims a headline increase (+17%) in decommissioning cost and contingencies. This
    increase of cost estimates does not affect the current MFF and, as per the information currently
    available, is not linked to any extension of the programme scope and the programme end date is
    confirmed. Bulgaria has increased the national contribution so that the residual financing gap is
    about EUR 92 million. At this point in time the cost revision has not been yet agreed by the
    Commission; Bulgaria needs to provide full justification of the revised cost estimates. The formal
    revision process should be completed in 2018 in the context of the adoption of the new detailed
    implementation procedures as per Articles 7 and 9 of the relevant Regulation5
    add will be taken
    into account during the negotiations for the next programming period.
    In both Bulgaria and Slovakia, the residual financing gap beyond 2020 is in the range of EUR 80-
    90 million per Member State.
    National contribution. The mid-term evaluation showed that the achieved levels of national
    contribution appear fit to sustain proper efficiency; nonetheless co-financing is not
    established in the legal basis, thus creating uncertainties that should be removed. Moreover, the
    analysis showed that increasing levels of national contribution are a necessary but not sufficient
    condition to set the right incentives for timely and efficient decommissioning. To this end, the
    explicit transfer of risks (cost overruns, delays) to the concerned Member States would have a
    greater impact. This practice has been already introduced to a certain extent under the current
    MFF where possible.
    Governance. The governance setup has ensured effective and efficient implementation of the
    programmes and compensated for the uncertainties mentioned on the national contribution
    aspects. Main factors of success were clear definitions of roles and responsibilities as well as a
    strengthened monitoring framework. The analysis has also identified areas for further
    improvement such as:
    (i) increased involvement of the Member States (programme coordinator) for increased
    ownership together with stronger accountability of the decommissioning operators (final
    beneficiaries);
    (ii) streamlining of procedures to enhance the timeliness of the management cycle;
    (iii) increased inter-comparability of the programmes' performance.
    Objectives. The mid-term evaluation confirmed that the programmes objectives of the NDAP
    (see Table 1) remain valid in the current MFF. Nevertheless, some of the expected results,
    milestones, target dates, as well as the corresponding performance indicators should be adapted
    in line with the latest updates of the decommissioning plans to allow for effective monitoring for
    the period 2018-2020.
    Although the reduction of the ultimate risk to the general population posed by these facilities
    while ensuring that the decommissioning is conducted in a safe manner have been the driving
    factors behind the NDAP, the mid-term evaluation noted that these aspects have not been well
    captured in the high level monitoring framework that is the basis for communication of the
    results to external parties (e.g. reporting to the Council and the Parliament). Any post-2020
    funding should therefore focus on explicit safety objectives monitored by means of dedicated
    performance indicators.
    13
    Knowledge gain. Finally the mid-term evaluation has highlighted that the experience gained so
    far from the projects implemented under the Kozloduy programme24
    and the Bohunice
    programme25
    provide a solid base of knowledge in the EU for conducting future
    decommissioning programmes of VVER type reactors (e.g. Czech Republic, Hungary, Germany,
    Finland). These EU co-funded programmes (including the Ignalina programme in Lithuania) may
    aim at becoming a solid benchmark for governance related issues and management practices such
    as cost estimation methodologies or planning.
    1.2.2. JRC decommissioning and waste management programme
    Under the current legal framework, a mid-term evaluation is not mandatory. The JRC is regularly
    reviewing its progress and performance, using independent external advice (D&WMP Expert
    Group, external consultants). Due to the high inherent risks of the D&WM programme, such as
    the risk of delays and resourcing risks, the programme has been selected for two audits by the
    Internal Audit Service (IAS) during the current MFF, one of which has been launched recently.
    The main outcomes and recommendations, as well as their follow-up by JRC, are summarised
    below. These recommendations together with those from the group of experts should further help
    JRC to improve the performance of its programme.
    Continuous technical advice by the D&WM Expert Group
    In managing the D&WM programme, the JRC is regularly advised by a group of independent
    European decommissioning experts (biannual meetings and additional ad-hoc meetings). Their
    advice relates to the decommissioning and radioactive waste treatment strategy, the available
    technology, technical aspects of the organisation and any other aspects relating to the programme
    (see section 5.2.1).
    Findings from external reviews and past audits
    The progress of the programme and its budget is periodically reviewed by external experts. Back
    in 2011, the experts found overall evidence that the activities on the different sites were on track,
    despite some delays, and that the plans and cost estimates for future decommissioning were
    established in a coherent way. Nevertheless, several uncertainties and risks were identified,
    which to a large extent were related to the long-lead times involved: figures were considered in
    many cases based on best estimates, with no or only few provisions to cover for uncertainties,
    particularly for the projects planned in the longer term (i.e. after 2020). The experts emphasised
    the importance of assessing in detail the expected amounts of waste, and encouraged JRC to
    investigate managerial and technical measures which should be taken in order to limit waste
    volumes and to reduce to the extent possible any uncertainties on the costs related to their future
    disposal.
    In 2014/2015, the IAS audited the financial aspects of the D&WM programme26
    . It concluded
    that the current operational set-up provides reasonable short-term assurance for achieving the
    JRC's objectives. However, such a short-term assurance is not enough for covering the needs of
    such a long-term complex programme. Among other recommendations, IAS confirmed the
    24
    At Kozloduy, for example, the Plasma Melting Facility represents a state-of-the-art equipment to achieve very
    high volume reduction of radioactive waste. It is the second application in the domain of nuclear waste
    management in the world. Demand for such cost-effective technologies can be expected to grow in coming years.
    25
    JAVYS – the decommissioning operator and final beneficiary in Slovakia – has included as an objective in its
    organizational strategy the leverage of gained experience into future commercial opportunities. So far the
    company has acquired on the international decommissioning market contracts in the area of radioactive waste
    management with the Czech company ČEZ (NPPs Dukovany and Temelín) and for the Italian company SOGIN
    (NPP Caorso).
    26
    Audit on Nuclear Decommissioning and Waste Management Programme at the JRC – Financial Aspects, IA – 14
    – 06 (224); Final Report (Ares(2015)2299901)
    14
    necessity of regular in-depth assessments, with focussed review of the decommissioning budget,
    paying special attention to the assessment of fixed costs and to the improvement of current
    estimates (Very Important Recommendation). IAS also looked at the mid-term planning needs in
    the field of human resources.
    Recent improvements
    Following these consistent recommendations for improving the cost estimates, and in light of the
    new strategy 2017 (see section 1.1.2), JRC sites with the support of external consultants, re-
    assessed in more detail their waste inventory and revised their decommissioning planning. A
    harmonised approach, based on recent international recommendations for estimation of
    decommissioning costs, has been applied to determine expected costs on each site. The new
    budget forecast (as of December 2017) includes contingencies, depending on the level of
    uncertainty associated with the respective activities and the external conditions at the different
    locations. The new strategy and budget forecast was reviewed by the D&WM Programme Expert
    Group and received a positive opinion at the end of the process. Still, significant uncertainties
    affect the timelines and the cost estimate for the different sites, inherent to the long-lead times for
    nuclear decommissioning and delays caused by the host Member State.
    New IAS Audit
    The IAS has launched a new audit on the D&WM programme implementation27
    . A draft Scoping
    Memo has been received on 13 March 2018. One of the main risks identified is in relation to the
    evolution of the planned activities in the period 2021-2060, which does not appear compatible
    with flat budget allocations as noted in JRC's updated strategy. The increase of operational
    D&WM programme activity covering multiple JRC sites will also impact the overall
    management strategy and need of internal JRC resources. The variable and unpredictable level of
    expenditures makes it difficult to manage the budget.
    Moreover, the dedicated D&WM budget line cannot be used for administrative expenses. In light
    of the expected increase of decommissioning activities at the different sites, continuing financing
    decommissioning staff from the Euratom Research and Training framework programme bears the
    risk to penalise JRC's research work programme in the future. The current trend of the
    Commission to reduce staff as well as the fact that the D&WM relies heavily on intra-muros is
    also conflicting with the need to ensure knowledge transfer on long-term.
    Other risk factors identified are related to the additional costs due to delays, the complexity of
    contracts to be managed, the difficulty of implementation of such a multi-site programme and the
    operational consequences of the long-term risk factors.
    The final Audit Report is expected in mid-2018. The findings of the IAS will further help JRC to
    improve programme performance in the future.
    27
    Launch of the 2018 IAS Audit on Nuclear Decommissioning and Waste Management Programme
    implementation in DG JRC, as notified in the Announcement Letter (Ares(2017)5064966)
    15
    2. THE OBJECTIVES
    1.3. Challenges for the programmes of the next MFF
    The key aim in nuclear decommissioning is the progressive removal of hazards inherently
    associated to the concerned installations. This process is stepwise in nature, mainly because the
    removal of major batches of radioactive materials is obtained over several stages. The reduction
    of the safety measures and associated costs evolves likewise.
    The key aim of the programmes is the progressive removal of hazards inherently associated to the
    concerned installations, however the programmes face different challenges. The differences
    mainly originate from the type of nuclear facilities covered, and the respective responsibilities of
    the Commission.
    1.3.1. Kozloduy programme (BG) and Bohunice programme (SK)
    At this point in time the decommissioning operators28
    are focussing on dismantling activities.
    Slovakia has advanced the most and is currently carrying out decontamination and dismantling in
    the reactor building at the Bohunice site, while in Bulgaria at the Kozloduy site decontamination
    and dismantling are well advanced in the auxiliary buildings and have started in the reactor
    buildings.
    These programmes are on track to accomplish the specific objectives with the funding provided
    in the current MFF (2014-2020) and a clear trend towards increased efficiency was observed
    throughout the monitoring activities as confirmed by independent experts29
    .
    Safety challenges
    Progress in the implementation of the Kozloduy and Bohunice programmes in the current MFF
    (2014-2020) has led already to a significant decrease in radiological hazard to the general public,
    because the most important sources of radiological hazards are tackled in the current MFF (e.g.
    decontamination and dismantling of the reactor primary cooling circuits and cores, and
    completion of waste management routes). Technical and technological challenges have been
    coped with successfully thus far. For the future challenges, knowledge sharing and synergies are
    key to ensure continued success, provided that the reactors are of the same model.
    The availability of financing in a timely manner is a crucial element for ensuring nuclear safety
    and the protection of the workers and the EU citizens. In case of insufficient funding, delays
    could be incurred with subsequent extra-costs, safety implications and increased risk of loss of
    unique expertise.
    In case of continuing the programmes after 2020 in Bulgaria and Slovakia, the budget estimates
    are reduced to less than one fourth compared to the current MFF. The annual average amounts
    (commitments) needed in the scenario with unchanged policy (i.e. continuation of the
    programmes) are shown in Annex 2.
    The EU funding under the next MFF and the allocated national contributions will cover the
    completion of the programmes in Bulgaria and Slovakia, thus addressing all safety challenges. In
    Slovakia, the funding may be over before the mid-term of the next MFF.
    28
    SERAW / Д А (State Enterprise Radioactive Waste / Дъ ав ияти „ а и актив и т а ъци”)
    in Bulgaria;
    JAVYS (Jadrova a vyradovacia spolocnost, a. s. / Nuclear and Decommissioning Company) in Slovakia
    29
    "Support to the mid-term evaluation of the Nuclear Decommissioning Assistance Programmes", EY, An
    evaluation for the European Commission DG Energy, 2018
    16
    Social challenges
    The social impact in the concerned regions caused by the shutdown of the reactors was initially
    important. Kozloduy is located in the Vratsa district (BG) which is one of the poorest areas in
    Bulgaria with a high unemployment rate30
    . Bohunice is located in the Trnava region (SK) which
    has a low unemployment rate31
    ; social challenges are therefore less significant in Bohunice than
    in Kozloduy.
    Nuclear power plants in operation are located on both sites (Kozloduy NPP Units 5 and 6;
    Bohunice V2 NPP).
    In 2017 under the Kozoduy programme approx. 650 full time equivalents were employed. Under
    the Bohunice programme 235 full time equivalents are currently working.
    Other available EU instruments may be deployed in the regions ensuring this way synergies and
    complementarities. For example, the European Regional Development Fund (ERDF), the
    European Social Fund Plus (ESF+) and the Cohesion Fund could support measures to accompany
    the related social and economic transition, including also energy efficiency and renewable energy
    measures as well as certain other activities not linked to radiological safety processes. As such
    these Funds can create additional activities in the concerned regions and utilise the locally
    available expertise as a major driver of job creation, sustainable growth and innovation. Similarly
    synergies should be explored with FP9 and / or the Euratom Research and Training programme
    in areas such as technology development and testing, as well as training and education.
    1.3.2. JRC decommissioning and waste management programme
    The D&WM programme covers the decommissioning of a variety of experimental research
    nuclear facilities, and the management of non-standard spent fuel and historical waste. This is
    notably a key distinguishing feature of this programme in relation to the 'Kozloduy' and
    'Bohunice' programmes which have to deal with power generating reactors. Additionally, as
    owner and nuclear operator under national laws of the nuclear facilities, JRC has the prime
    responsibility for the safe management from generation to disposal of the spent fuel and
    radioactive waste it has generated (Article 7 of Directive 2011/70/Euratom), until transfer of
    ownership to the host Member State or release of the facilities from regulatory control. Actually,
    JRC is implementing the D&WM programme as license holder in four different Member States.
    Uncertainties due to external factors
    The four JRC sites face uncertainties of different types. For example, in Ispra, where the
    D&WMP is more advanced, the complex and long licensing/authorisation process is causing
    significant delays, both for the management of radioactive waste and for the decommissioning of
    the facilities.
    Italy: Lack of criteria for waste management
    Directive 2011/70/Euratom on the safe and responsible management of radioactive waste and
    spent fuel obliges each Member State to establish a national programme (to be communicated to
    the Commission) which translates the national policies into concrete plans of actions, in order to
    ensure that progress is made.
    30
    Average unemployment rate in the Vratsa province in the first half of 2016 was 19.0 % compared to the national
    average of 9.4%.
    [https://ec.europa.eu/eures/main.jsp?countryId=BG&acro=lmi&showRegion=true&lang=en&mode=text&region
    Id=BG0&nuts2Code=%20&nuts3Code=null&catId=9574]
    31
    Unemployment rate in Trnava region in January 2018 was 2.06% being the lowest rate in Slovakia.
    [http://www.upsvar.sk/media/medialne-spravy/v-januari-2018-miera-evidovanej-nezamestnanosti-v-sulade-s-
    dlhodobym-trendom.html?page_id=764912]
    17
    Italy has not yet adopted such a national programme, formulating how it would implement
    concrete radioactive waste and spent fuel management solutions. This has two essential
    consequences:
     JRC has no information how the radioactive waste generated during operation and
    decommissioning needs to be conditioned in order to transfer it to the Italian radioactive
    waste management organisation. This is commonly referred to as "waste acceptance criteria".
    In absence of such criteria, there is a risk of having to re-condition the materials a second
    time – which is a costly operation with increased safety risks due to the radiological hazards
    involved. Therefore, such operations often require to be put "on hold" until the acceptance
    criteria are defined, potentially leading to overall delays in the decommissioning process32
    .
     JRC cannot transfer the radioactive waste generated during decommissioning directly to the
    Italian radioactive waste management organisation, i.e. the "waste management route" is not
    open. As a consequence, capacity for storing the materials has to be maintained on the site
    (see "Technical and Technological challenges" below).
    Italy: pending authorisations for decommissioning
    Decommissioning of nuclear facilities is subject to authorisation, a process which in Italy
    involves agreements from several State Ministries. For each decommissioning phase, the
    activities to be performed have to be described in detail, including safety, environmental and
    radiation protection implications as well as the initial and final state of the site and the solution
    envisaged for waste management and waste disposal. The identification and analysis of possible
    hazard and of accident scenarios for each phase of decommissioning must be addressed in the
    application, together with implication for the outside emergency plan and proposal for its
    updating.
    So far, only one laboratory has been fully decommissioned and released from regulatory control
    as this did not require this authorisation process. Dismantling of some internal parts of the
    installations in Ispra is currently possible within the existing licenses for running the facilities,
    but only if special ad hoc authorisations are granted by the Safety Authorities. The
    implementation of the 'Settlement Agreement' that was signed in 2009 between Italy and the
    Commission, transferring over the responsibility for the decommissioning of one of the two
    reactors at the Ispra site to the Italian authorities, started only in 2018.
    The JRC Ispra decommissioning programme end date has already been postponed from 2028 to
    2030, and it is currently scheduled for 2038.
    Petten: Uncertainties regarding operational life time
    In Petten, the end of operation of the High-Flux Reactor (HFR) was not defined until recently. On
    November 21, 2017 the Commission received the Notification of Investment for the new Dutch
    research reactor (PALLAS), to be built in Petten. According to this notification, HFR would be
    shut down once PALLAS becomes operational (scheduled for 2025). However, there is no
    guarantee that the new reactor will be built. For this, the Dutch Authorities should give final
    authorisation (after completion of the Environmental Impact Assessment, licensing etc.)
    32
    JRC has mitigated the financial risks for potential re-conditioning by signing a 'Settlement Agreement' with the
    Italian State in 2009, as to which the costs have a certain ceiling; this agreement however was only recently
    recognised by Italy. The agreement ("Accordo Transattivo … sui principi governanti le responsabilita' di gestione
    dei rifiuti radioattivi nel sito del Centro Comune di Ricerca di Ispra", signed on Nov 27, 2009) is based on three
    commitments by the Italian Government: take charge of decommissioning the Ispra-1 reactor; take ownership
    and manage the interim storage facility and the conditioned waste stored therein; cap costs for potential re-
    conditioning of waste. The agreement was pending implementation by the Italian Government. Only recently it
    was recognised by publishing the Italian Budget Law for 2018 (Leggi di Stabilità) which included provisions for
    2018 to implement one of Italy's commitments, namely that to take charge of one of the two reactors at the Ispra
    site
    18
    Cost increases
    Costs for delays currently amount to EUR 10 million per year for the safe conservation of the
    nuclear facilities at the Ispra site, in addition to the staff costs (58 members of JRC staff paid
    from Euratom R&D budget).
    Today, the best available cost estimate of decommissioning is significantly higher than past
    estimates (EUR 1.6 billion vs EUR 0.9 billion forecasted in 2013). Real costs could be even
    higher at the time of completion of the programme, depending on which risks actually
    materialise.
    In Ispra, the current estimate for waste disposal (EUR 138 M) is conditional to high uncertainties
    due to the lack of any national disposal path for radioactive waste and nuclear material (lack of
    national repositories and definition of Waste Acceptance Criteria by the host Member State).
    Belgium, Germany and the Netherlands have established waste disposal paths for low level
    waste. It has to be noted that waste disposal costs increased by 60% in Belgium within the last 5
    years. The cost estimate in Karlsruhe does not include the disposal of nuclear material and spent
    fuel due to the current lack of a disposal path. These costs will be incurred in the frame of future
    decommissioning activities in Karlsruhe (around 2030 and beyond).
    Technical and technological challenges
    The nuclear facilities at the JRC Ispra site include two research reactors (ESSOR and Ispra1), a
    hot-cells laboratory building, a former test facility for nuclear material, a cyclotron building, and
    a liquid treatment station with 'tank farm'. Even though the nuclear research facilities have been
    shut down long time ago, the decision to go ahead with their decommissioning was postponed for
    different reasons. As regards the ESSOR reactor, the final decision to proceed with
    decommissioning was taken in 1998.
    Italy is only at the beginning of the process of identifying a national radioactive waste repository,
    and all the waste generated by the operation and decommissioning of nuclear installations in Italy
    is currently stored in the sites of origin. In this context, JRC Ispra has started to build new waste
    treatment and storage facilities on its premises to manage its own radioactive waste until the final
    Italian repository will be available.
    Part of the JRC Ispra premises was used for the treatment and storage of waste and nuclear
    material. In the frame of the D&WM programme, new facilities for waste treatment,
    characterisation and safe storage have been, or are being established. The establishment of state-
    of-the-art procedures for the safe treatment of historical waste is one of the key challenges of the
    programme. The knowledge gained by JRC in this kind of "pilot tests" would be a valuable
    contribution to Member States national decommissioning programmes. Where appropriate from
    licensing, technical and financial point of view, external nuclear facilities are used to process
    waste and nuclear material.
    In comparison with the technological, administrative and environmental challenges JRC Ispra is
    facing, the decommissioning activities in Karlsruhe (low activity laboratories and Hot Cells),
    Geel (low activity laboratories and two accelerators) and Petten (one research reactor) are more
    straightforward: waste disposal paths have been established by the host Member States, and
    future decommissioning will build on the experience gained by JRC during the R&D operation of
    the facilities (e.g. regular disposal of obsolete laboratory equipment and waste).
    Availability of adequate resources
    Decommissioning is a long-term industrial activity which requires adequate resources, in terms
    of budget and staff, throughout the programme. Budget, as well as the JRC staff dealing with
    19
    decommissioning, should be available throughout the duration of the decommissioning activities
    which are expected to peak around 2025 and remain high for several years until circa 2040.
    A specialised workforce is required, with skills in the technical field (engineering /physics
    /chemistry /radiation protection), in industrial project and contract management, and with specific
    knowledge in the licencing processes of the four host Member States. In the current framework,
    the workforce is stemming and paid from the Euratom R&D budget. If – in light of the current
    staff reduction strategy of the Commission – DG JRC has to maintain the number of staff or even
    reduce it, increasing the number of staff in decommissioning in the future would mean decreasing
    the number of staff engaged in other important activities of JRC (research, policy support, etc.).
    The decommissioning programme as an "industrial activity" depends on strong administrative
    support to prepare and manage high-volume and technically complex contracts (legal advice,
    procurement staff). In the past, the preparation of such contracts, moreover their implementation,
    were frequently behind schedule and caused additional delays and budget underspending (on
    average 20% of unspent yearly payment allocations in the current MFF). Unexpected technical
    difficulties or contamination levels are possible in any decommissioning project, and might
    require additional licensing, negotiations and/or lawsuits with existing contractors, and
    preparation of additional contracts. Flexibility in budget allocation would be needed throughout
    the programme.
    1.4. Objectives of the programmes of the next MFF
    1.4.1. General objectives
    The 'Kozloduy' and 'Bohunice' programmes aim to assist Bulgaria and Slovakia in managing
    the radiological safety challenges of the decommissioning process.
    The D&WMP programme pursues the decommissioning of the Commission (JRC) sites, and
    explores and develops options for anticipated transfer of decommissioning and waste
    management liabilities to the JRC host Member States.
    These two main general objectives are complemented by the aim of enhancing the EU added
    value of the programme through dissemination of knowledge (thereby generated) to all EU
    Member States on the decommissioning process.
    Finally, a key policy objective remains the increase of Member States' ownership of the
    decommissioning and waste management processes.
    1.4.2. Objectives of the Kozloduy and Bohunice programmes
    The specific objectives for the programmes in Bulgaria and Slovakia need to be adapted to the
    actual progress of the decommissioning programmes and the need to foster knowledge sharing
    and potential synergies.
    The disposal of spent fuel and radioactive waste in a deep geological repository is excluded from
    the scope of the programmes, and has to be developed by each Member State in its national
    programme for the management of spent fuel and radioactive waste as required by the relevant
    directive33,34
    . The Slovak national programme covers the realisation of a deep geological
    33
    Council Directive 2011/70/Euratom of 19 July 2011 on establishing a Community framework for the responsible
    and safe management of spent fuel and radioactive waste, OJ L199, 2.8.2011, p. 48-56.
    34
    Report from the Commission to the Council and the European Parliament on progress of implementation of
    Council Directive 2011/70/Euratom and an inventory of radioactive waste and spent fuel present in the
    Community's territory and the future prospects – C(2017) 236 final.
    20
    repository and schedules it in 2065; however until 2020 the alternative option to explore solutions
    for disposal in other countries will be also considered. The Bulgarian national programme
    presents a cut-off date in 2030, therefore does not cover the funding for a deep geological
    repository.
    Three specific objectives reflect the need to progress in the removal of radiological hazards:
    (1) Finalise dismantling and decontamination of the reactor primary circuit and big components
    in accordance with the decommissioning plan; progress has to be measured by the quantity
    and type of materials removed as well as earned value;
    (2) Finalise safe management of the decommissioning and legacy waste up to interim storage or
    to disposal (depending on the waste category), including the completion of the waste
    management infrastructure where necessary. This objective has to be accomplished in
    accordance with the decommissioning plan; progress has to be measured by the quantity and
    type of safely stored or disposed of waste as well as earned value; and
    (3) Continue downgrading of radiological hazards; this objective has to be measured through the
    safety assessments of the activities and the facility, identifying ways in which potential
    exposures could occur and estimating the probabilities and magnitude of potential
    exposures. Removal of the facilities35
    from regulatory control is planned by 2025 in the
    Bohunice programme and by 2030 in the Kozloduy programme.
    The plans shall include a proper set of milestones (output, date and budget) and target amounts.
    Other two specific objectives reflect the general policy objective to increase Member States'
    ownership:
    (4) Specify the maximum level of EU co-financing both in relative and absolute terms. The EU
    funding provided under the next MFF is the final allocation for the completion of the
    Bohunice and Kozloduy programmes;
    (5) Support national initiatives to develop implementing agencies to ensure local capacity and
    increased ownership to govern decommissioning and waste management.
    1.4.3. Objectives of the JRC decommissioning and waste management
    programme
    The main general objective of the JRC D&WM programme is to pursue the decommissioning of
    the Commission's JRC installations in four sites: JRC-Geel in Belgium, JRC-Karlsruhe in
    Germany, JRC-Ispra in Italy and JRC-Petten in the Netherlands and to safely manage the spent
    fuel and radioactive waste until the transfer of responsibilities to the host Member State.
    Activities financed under this programme in the period 2021-2027 have to deliver the following:
    (1) For all sites:
    Explore and develop options for anticipated transfer of decommissioning and waste management
    liabilities to the host Member State.
    (2) At JRC-Ispra (depending on release of the relevant authorisations by the Italian Safety
    Authorities):
    35
    Refers exclusively to Kozloduy nuclear power plant units 1-4 and Bohunice V1 nuclear power plant.
    21
     Retrieval, treatment and safe storage of the historical waste until transfer of ownership to
    the host Member State;
     Retrieval, treatment and safe storage of nuclear material and spent fuel until transfer of
    ownership to the host Member State;
     Decommissioning of licensed nuclear facilities;
     Safe management of decommissioning radioactive waste and materials.
    (3) At JRC-Karlsruhe:
     Decommissioning of obsolete equipment;
     Safe management of decommissioning radioactive waste and materials;
     Reduced inventory of obsolete nuclear material and spent fuel;
     Decommissioning of shut-down facilities;
     Preparatory phases of the decommissioning of building parts
    (4) At JRC-Petten:
     Safe management of historical and decommissioning waste and materials;
     Reduced inventory of obsolete nuclear material and spent fuel.
     Preparatory phases of the decommissioning of the HFR, in coordination with the current
    operator
    (5) At JRC-Geel:
     Decommissioning of obsolete equipment;
     Safe management of decommissioning radioactive waste and materials.
    The D&WM programme shall contribute to the JRC host Member States national programmes on
    their implementation of the Council Directive 2011/70/Euratom on the responsible and safe
    management of spent fuel and radioactive waste. To this end, the costs for the disposal of spent
    fuel and radioactive waste in a final repository are included in the scope of the programme.
    1.4.4. Common specific objectives
    An additional specific objective should reflect the opportunity and need to create and share
    knowledge for all EU Member States managing decommissioning programmes. When possible,
    additional synergies should be also developed and exploited.
    The merger in one instrument of the decommissioning activities in Bulgaria and Slovakia, and of
    the JRC will build synergies between the two programmes and additional in-house know-how for
    the Commission to explore and develop options for anticipated transfer of decommissioning and
    waste management liabilities to the JRC host Member States. As mentioned, synergies with the
    European Regional Development Fund (ERDF), the European Social Fund Plus (ESF+) and the
    Cohesion Fund can be strengthened in the next programming period. Similarly synergies should
    be explored with FP9 and / or Euratom Research and Training programme in areas such as
    technology development and testing, as well as training and education.
    (1) Develop ties and exchanges among EU stakeholders (e.g. Member States, safety authorities,
    utilities and decommissioning operators) and
    22
    (2) document explicit knowledge and make it available through multi-lateral knowledge
    transfers on decommissioning and waste management governance issues, managerial best
    practices, and technological challenges, with a view to develop potential EU synergies.
    Progress is to be measured by the number of knowledge products created and their outreach.
    23
    3. PROGRAMME STRUCTURE AND PRIORITIES
    The programme for Bulgaria and Slovakia is indirectly managed through the European Bank for
    Reconstruction and Development and a national agency in Slovakia. Keeping the
    decommissioning of these reactors under a dedicated spending programme implies that
    implementation continues seamlessly through the established implementing bodies. However, the
    establishment of a national agency in Bulgaria should be assessed.
    The programme for the decommissioning of the Commission's sites is managed directly by the
    JRC.
    Having the two programmes under one instrument provides the proper flexibility to maximise
    effectiveness and efficiency, ensure knowledge sharing and synergies, and support JRC exploring
    and developing options for anticipated transfer of decommissioning and waste management
    liabilities to the JRC host Member States.
    1.5. Kozloduy programme and Bohunice programme
    The common legal basis for the Kozloduy programme and Bohunice programme is the Euratom
    Treaty. Article 203 of the Treaty establishing the European Atomic Energy Community (EAEC)
    states that "the Commission shall establish uniform safety standards to protect the health of
    workers and of the general public and ensure that they are applied. If action by the Commission
    should prove necessary to attain this objective and the Euratom Treaty has not provided the
    necessary powers, the Council shall, acting unanimously on a proposal from the Commission and
    after consulting the European Parliament, take the appropriate measures."
    The actions to be funded post-2020 will be derived from the latest version of the
    decommissioning plans and are generally responding to the safety objective. The main priority
    for the programmes is to ensure timely availability of funds for the accomplishment of the safety
    objective.
    In order of importance the priorities for the programmes are:
    (i) sharper focus on safety (nuclear safety, protection of workers, public, and the
    environment);
    (ii) dissemination of knowledge for the EU nuclear decommissioning market;
    (iii) incentivised and enhanced performance through increased ownership;
    (iv) simplification and synergies;
    (v) solidarity.
    Based on the already good established practice of the current MFF, whereby the focus of the
    programmes was restricted to decommissioning only, the programmes should further focus on
    activities strictly related to the delivery of the general and specific objectives and the EU added
    value, i.e. removal of radiological hazards and creation and dissemination of relevant knowledge.
    The established decommissioning plans will continue to serve as the baseline, defining this way
    the precise scope for EU assistance. At the same time incentives to pursue decommissioning
    should be embedded in the funding mechanism, including time limitations and appropriate levels
    of national contribution from the beneficiary Member States.
    The aspect of EU solidarity also deserves the right level of political attention, because it
    underpinned the agreements between the two Member States and the Union when the decision to
    prematurely shut-down those reactors was taken.
    24
    Hence, it is important that the programme be prioritised for further EU support in the next MFF
    (2021-2027) as it has the potential for achieving notable EU-added value both in terms of safety
    and knowledge gain.
    1.6. JRC decommissioning and waste management programme
    As nuclear operator under Italian, Dutch, German and Belgian laws, JRC is responsible in the
    four host Member States for the safe management from generation to disposal of the spent fuel
    and radioactive waste it has generated. This includes the provision of adequate financial and
    human resources to ensure the safety of spent fuel and radioactive waste. In this context, the
    availability of the necessary human resources, as well as volume and flexibility of the budget
    shall be ensured.
    Following the proposal of the high level Working Group of Commission Services (see 1.1.2), the
    handing over of JRC nuclear facilities including nuclear material present financial and legal
    benefits for JRC – it would ensure that JRC would cease to be responsible for decommissioning
    and waste management, would no longer bear the associated costs and would release JRC from
    its obligations (for the safety of spent fuel and radioactive waste management as well as for
    decommissioning activities). Therefore, the exploration and development of anticipated transfer
    of liabilities to the JRC host Member States should be prioritised.
    The handing-over of JRC's nuclear facilities to the respective host Member State is possible.
    Such transfers occurred in the past in some of the concerned Member States. Any such financial
    settlement can take different forms, for example, it could be paid over several multiannual
    financial framework periods, given the length of the decommissioning process.
    It is important to bear in mind that currently the situation needs to be differentiated: in Belgium,
    Germany, and the Netherlands waste acceptance criteria are defined and therefore, the situation is
    relatively more stable than in Italy where the waste routes are not clear in the national
    programme. The higher uncertainties related to the JRC Ispra decommissioning plan are due to
    the current absence of waste acceptance criteria and the absence of the final disposal facility.
    A successful hand-over to Member States will also allow to free JRC human resources for
    effective transfer of explicit knowledge on decommissioning and waste management issues to
    Member States, in line with the common specific objectives (2.2.3).
    Should the negotiations with the Member States encounter difficulties, the JRC would need to
    ensure sufficient staff levels (adapted to the volume and pace of activities), to carry out the safe
    decommissioning of its facilities and fulfil its legal obligations also with regard to waste
    management. JRC will also ensure the continuous dissemination of knowledge gained throughout
    the implementation of the programme at the different sites.
    25
    4. DELIVERY MECHANISMS OF THE INTENDED FUNDING
    1.7. Kozloduy programme (BG) and Bohunice programme (SK)
    In the context of the mid-term evaluation the current NDAP has been benchmarked with three
    ‘comparator’ instruments36
    : Connecting Europe Facility (CEF), Budget Support aid delivery
    mechanism and ESIF major projects. The benchmark focused on the identification of relevant
    best practices concerning the governance, the programme and project management and financial
    management.
    The benchmark showed that the performance monitoring framework for the current NDAP is
    generally in line with best practice - in particular practices in Budget Support operations – given
    that a results-based performance monitoring is in place. In this respect the NDAP could be
    improved by linking additional funding to the achievement of pre-defined targets.
    As sought by the current NDAP, all 'comparator' instruments seek to ensure strong national
    ownership of project implementation through early buy in and strong Member State involvement.
    Member States are involved early on in the development of the projects or programmes and have
    input at key phases.
    CEF and ESIF have a clearly defined framework for EU co-financing, with minimum and
    maximum EU co-financing rates set out in the legal base. Unlike CEF and ESIF, the NDAP has
    no formalised framework for EU co-financing at the moment.
    All instruments, the current NDAP inclusive, offer a fully multi-annual rather than annual
    framework for programming. While 'comparator' instruments all imposed annual monitoring and
    reporting requirements (similar to NDAP), none had in place an annual cycle for programming
    and commitments (in contrast to NDAP). Projects are implemented in line with their approved
    work plans. For CEF and major projects, specific approval is necessary prior to funding as well
    as for substantive deviations from the approved programme of works or approved budget.
    The defining feature of major projects is the specific approval procedure to which they are
    subject to. This includes a number of analyses carried out by the Commission services with the
    aim to ensure the quality of the project proposal, its feasibility, maturity and its utility. The
    NDAP delegates this role to the implementing bodies that are entrusted budget implementation
    tasks via a delegation agreement.
    A new financial regulation is being prepared to provide the EU with enhanced tools to implement
    the budget. The design of a new delivery mechanism will have to make use of the new features
    proposed by the financial regulation.
    Based on the above, the following three policy options should be considered in assessing the
    impact of the Kozloduy and Bohunice programmes in the next MFF:
    (i) Policy option 1 - Discontinuation of the programmes,
    (ii) Policy option 2 - Programmes under cohesion policy,
    (iii) Policy option 3 - Programmes combined with the decommissioning of JRC sites
    (baseline option).
    36
    These three comparators were selected because they represent a variety of different approaches for programme
    implementation and are used to deliver large-scale projects, including notably in the energy sector.
    26
    1.7.1. Policy option 1 - Discontinuation of the programmes
    Under Option 1 no further financial EU assistance would be provided and consequently the two
    Member States would have to guarantee safe completion of their decommissioning programme
    with own national resources.
    As mentioned under section 2.1.1 above, in case of insufficient funding, there is a risk of
    rendering the whole decommissioning process more lengthy and costly, as well as a result in
    possible safety implications and risk of loss of unique expertise.
    Firstly, in Bulgaria and Slovakia significant decrease in radiological hazard to the general public
    has already been accomplished by the programmes.
    Secondly, the Commission services have found in a previous study37
    that the State budgets of the
    concerned Member States appear able to absorb the additional financing needs.
    Finally, the national policies and programmes which are established by the Member States in
    application of the 'Radioactive Waste' directive include the management of spent fuel and
    decommissioning waste from the concerned facilities and the associated cost estimates until the
    completion of the programmes.
    In summary, given that national policies and programmes are in place, key safety objectives have
    been met already, and the national economies appear fit for bearing future charges, the
    discontinuation option may appear viable in some respect.
    However, in such a scenario the Union would have no more leverage on the timely execution of
    the safety actions within the timescales set out in the approved decommissioning plans.
    Moreover, the discontinuation of the programmes could harm the reputation of the EU in
    Bulgaria and Slovakia as they had to shut down the six reactors on request by the EU at the time
    of the accession negotiations. They were relying on Union support for the decommissioning as
    well as for measures mitigating the important effects to their economies due to the loss of inland
    energy production38
    .
    These risks should be assessed also in view of the reduced average yearly needs of the
    programmes altogether, and of the increased programmes' effectiveness and efficiency obtained
    during the current MFF.
    1.7.2. Policy option 2 - Programmes under cohesion policy
    Cohesion policy is the Union's main investment policy, aiming to strengthen economic, social
    and territorial cohesion and reduce disparities among regions. It is a major driver of job creation,
    sustainable growth and innovation in Europe’s diverse regions.
    As a result of a performance audit on the NDAP, in 2016 the ECA recommended39
    discontinuing
    dedicated spending programmes after 2020 and considering access to ESIF for nuclear
    37
    "Nuclear Decommissioning Assistance Programme (NDAP) – Assessment of the robustness of the financing
    plans considering the economic-financial-budgetary situation in each concerned Member State and of the
    relevance and feasibility of the detailed decommissioning plans", Deloitte, NucAdvisor, VVA Europe, A study
    prepared for the European Commission DG Energy, 2016
    38
    For example Slovakia – as a consequence of the shutdown of Bohunice V1 NPP – changed from an exporter of
    electricity to an importer country for electricity.
    39
    Recommendation 5: dedicated funding programmes for nuclear decommissioning in Lithuania, Bulgaria and
    Slovakia should be discontinued after 2020. If a clear need for the use of EU funds beyond 2020 is established, in
    one or more of the three Member States, any future EU funding proposed by the Commission and agreed by the
    legislator should include the right incentives to pursue decommissioning, including by being time limited and by
    being based on appropriate levels of Member State co-financing. One way to do this would be to consider
    27
    decommissioning activities. This recommendation was made with the aim to create the right
    incentives to pursue decommissioning and adhere to the strict rules on co-financing applicable
    under ESIF (i.e. fixed maximum EU co-financing rates). The Commission partially accepted this
    recommendation holding over its prerogative to decide based on an impact assessment (replaced
    by this ex-ante evaluation) in line with the requirements of the financial regulation and better
    regulation agenda with regard to proposals of new initiatives.
    It is worth recalling that in preparation of the current MFF (2014–2020) the NDAP was already
    revised to exclude all measures which were not strictly related to the decommissioning of the
    concerned facilities. As a consequence, support to energy related projects was taken out of NDAP
    as it could be supported through other EU funded measures such as ESIF.
    Currently, decommissioning of nuclear power stations is explicitly excluded40
    under ESIF
    (European Regional Development Fund and Cohesion Fund). Therefore, a possible funding of
    decommissioning under cohesion policy will lead to a fundamental change in the philosophy of
    these Funds, which are geared to growth objectives, notably in line with the priorities of the
    Europe 2020 strategy.
    Several arguments can be listed pro the extension of eligibility under cohesion policy to the
    decommissioning of these specific reactors:
    (i) simplification and reduction of administrative burden;
    (ii) well-established, proven and cross-cutting management and control systems;
    (iii) increased Member States' ownership of the decommissioning programmes, with clear
    requirements for national contributions;
    (iv) budgetary flexibility transferred to the Member States.
    In other words, implementation under the shared management mode could increase the Member
    States' ownership of the decommissioning programmes (if compared to the baseline scenario) and
    would allow Member States to prioritise decommissioning projects among other eligible projects
    under the cohesion policy funding.
    However, these advantages are offset by two substantial drawbacks:
    (i) making decommissioning an eligible activity under cohesion policy funding, will create a
    precedence that goes against the principles set by the Council Directive 2011/70/Euratom
    on the safe and responsible management of radioactive waste and spent fuel, whereby the
    costs for the management of these materials shall be borne by those who generated those
    materials; and
    (ii) shifting of budget between priorities is possible during the entire lifetime of the
    programme, therefore there is a risk of de-prioritisation of decommissioning in favour of
    other activities financed within cohesion policy.
    In addition, given the relatively small remaining size (both in time and in costs) of the
    programmes and the limited number of new projects remaining eligible for EU co-financing a
    change of the delivery mechanism would appear disproportionate at this stage.
    widening access to the European Structural and Investment Funds to allow nuclear decommissioning activities to
    be covered, fulfilling these conditions.
    40
    Article 3.3 Regulation (EU) No 1301/2013 of the European Parliament and of the Council of 17 December 2013
    on the European Regional Development Fund and on specific provisions concerning the Investment for growth
    and jobs goal and repealing Regulation (EC) No 1080/2006;
    Article 2.2 Regulation (EU) No 1300/2013 of the European Parliament and of the Council of 17 December 2013
    on the Cohesion Fund and repealing Council Regulation (EC) No 1084/2006.
    28
    1.7.3. Policy option 3 - Programmes as dedicated spending programme
    Safety remains at the heart of the Union policy priorities18
    . The fundamental need of safety has
    been the basis for the NDAP since their inception, i.e. since the pre-accession time. This need is
    still the main driver for continuing the programmes under safety policies.
    As a result of the NDAP mid-term evaluation the current governance setup has proven to ensure
    effective and efficient implementation of the programmes. Main factors of success are the clear
    definitions of roles and responsibilities as well as the strengthened monitoring framework.
    Each concerned Member State appoints a Programme Coordinator (deputy minister or state
    secretary rank) to be responsible for the programming, coordination and monitoring of the
    decommissioning programme, thus ensuring at national level the comprehensive oversight of the
    programme and enhancing access to information by the Commission in its supervisory role.
    Committees with monitoring and reporting functions are in place for each Member State, co-
    chaired by a Commission representative and the Programme Coordinators. The Committees are
    well equipped with a dashboard of key performance indicators and detailed targets, in order to
    steer the programmes through a well-informed assessment and decision making process. The
    detailed objectives and indicators (proposed by the three Member States and approved by the
    Commission) provide quantitative information to measure progress towards the specific
    objectives. Moreover, the Earned Value Management (EVM) methodology enhances the
    Commission's supervision on both effectiveness and efficiency with a positive trickle-down
    effect at national level.
    From a legal viewpoint, the base for the continuation of the programmes in Bulgaria and Slovakia
    is well identified. Nonetheless the analysis and the benchmark have also identified areas for
    further improvement to be achieved in the establishment of a new Regulation for the next MFF,
    should this policy option be selected.
    In particular on the EU co-financing issue, it is worth noting that presently national contributions
    are generally within the ranges defined under the ESIF, although the legal basis has not defined
    the due level of national contribution. While this approach created uncertainties, in the present
    financial framework levels of national contribution have increased compared to pre 2014-2020
    period. From a legal viewpoint there are no obstacles to introduce clearer criteria and provisions
    (in line with the ESIF ones); the decision in this respect remains truly political.
    Likewise, further increase of Member States ownership as well as stronger incentives can be
    devised in dedicated spending programmes, based on the other lessons learnt from 'comparator'
    instruments, such as limitation in time for the funding.
    The programmes are currently implemented by the EBRD in Bulgaria, and Slovakia as well as by
    a national agency in Slovakia (SIEA). The implementation via the national agency was
    established upon request by Slovakia in view of increasing ownership. Continuing the
    implementation of the programmes through the established implementing bodies would ensure
    stability in the safe decommissioning process. However, the establishment of a national agency in
    Bulgaria should also be assessed. This option would further increase the involvement of Bulgaria
    in the implementation of the Kozloduy programme.
    The progress achieved under the current NDAP in both Member States is significant. The
    existing monitoring tools – remarkably the EVM based methodology - have ensured that issues
    29
    that have occurred in the implementation of projects have been addressed in a timely and
    efficient manner to prevent delays41
    .
    With regard to the overarching aims in preparing the next MFF (2021-2027) namely agility and
    simplification, this policy option offers interesting solutions. The budget for the programmes in
    Bulgaria and Slovakia could be pooled with the Commission's own decommissioning activities
    (in JRC). This should allow for increased financial flexibility between decommissioning
    programmes financed by the Commission. As mentioned above, budgetary flexibility is
    necessary in view of the limited needs for the Kozloduy and Bohunice programmes to complete
    the decommissioning activities, and the needs also of the JRC decommissioning programme for
    flexibility of budget allocation resulting from uncertainty in the activities' schedule. Moreover
    this option creates opportunities for enhanced knowledge sharing and identification of potential
    synergies between the programmes.
    1.7.4. Policy options benchmark
    The risks associated to policy option 1 (discontinuation) can be summarised as such: EU would
    waive leveraging on the safety objectives of the NDAP as well as exploiting the knowledge
    gained in favour of other EU Member States; moreover, from a political standpoint, the solidarity
    principle underpinning the NDAP thus far would be disregarded by the Union with negative
    effect on the European sentiment in Bulgaria, and Slovakia.
    Policy options 2 and 3 are mainly differentiated in terms of theme (cohesion vs safety) and
    delivery mechanism (cohesion policy funding vs dedicated spending programme).
    Both solutions are fit for addressing the substantial needs of increased ownership by the
    beneficiary Member State and of stronger incentives to pursue decommissioning in a timely and
    efficient manner. However, policy option 3 responds more effectively to the needs of:
    (i) EU leveraging on the safety objectives;
    (ii) exploitation of the knowledge gain for the decommissioning of nuclear reactors EU wide;
    (iii) knowledge sharing and development of potential synergies amongst decommissioning
    programmes managed by the Commission;
    (iv) budgetary flexibility.
    Finally, given the progress achieved in Bulgaria and particularly Slovakia, the change of delivery
    mechanism at this point in time appears disproportionate with respect to the marginal benefits
    policy option 2 offers.
    1.8. JRC decommissioning and waste management programme
    As mentioned above, the JRC D&WM programme unlike other programmes, e.g. Horizon 2020,
    has no secondary legislation. Instead, it relies on the legal base provided by Article 8 of the
    Euratom Treaty.
    To this end and based on the Communication of the Commission "Historical Liabilities Resulting
    from Nuclear Activities carried out at the JRC under the Euratom Treaty – Decommissioning of
    obsolete Nuclear Installations and Waste Management" (COM(1999)114), the Programme was
    41
    For example: in the project for the decontamination of the primary circuits of the Bohunice V1 reactors the
    contractor chosen through an open procurement procedure failed to achieve the expected results. Initially the
    consequent delays impacted the critical path of the programme. However the project was put back on track and
    the decontamination was completed with excellent results. In parallel, through a review of the programme critical
    path, any impact was minimised and the end date of the programme (2025) is still valid.
    30
    initiated and a specific ad hoc budget line was created, in agreement with the European
    Parliament and the Council, following the principle of annuality.
    Outsourced services and supplies are financed by budget line (Chapter 10.05.01) that cannot be
    used for administrative expenses. As a result, the in house human resources necessary for the
    implementation of the programme (for management and supervision) are funded through the
    Euratom Research and Training framework programme.
    The variable and unpredictable level of expenditures in a given year (currently mainly related to
    the lengthy authorization procedures by national authorities and complex procurement and
    contract management) makes it difficult to manage the programme in line with the current
    budgetary and financial setup that is based on the annuality principle as it is not always possible
    to predict which payments will have to be made in a particular year. For example, payments have
    often been lower than expected, resulting in apparently "poor" budget execution.
    As described in 3.2, the handing over of JRC facilities to the host Member State presents
    financial and legal benefits for the Commission. This is possible and there is precedence of such
    transfers in certain of the Member States concerned.
    In light of the uncertainties around the D&WMP that may result in increasing volume and
    uncertainty of budgetary needs more budgetary flexibility is needed.
    Pooling the D&WM budget and the Kozloduy and Bohunice programmes would allow for certain
    financial flexibility. As described in 4.1.3, it would also create opportunities for effective
    knowledge sharing and identification of potential synergies between the programmes.
    5. HOW WILL PERFORMANCE BE MONITORED AND EVALUATED?
    Nuclear decommissioning programs are complex and long-lasting (flowing through several
    subsequent MFFs). Objectives are thus specifically defined for the short term (e.g. year, MFF)
    under the framework of a multiannual programme aimed at accomplishing the general objective,
    i.e. achieving a pre-defined end-state at the site as approved by the national nuclear regulator.
    1.9. Kozloduy programme and Bohunice programme
    1.9.1. Programming, monitoring and control system
    Under policy option 3 the programming, monitoring and control system will be further improved
    and streamlined with respect to the existing one; lessons learnt from the mid-term evaluation will
    be used in order to ensure continuous improvement.
    In 2013, the Commission modified the governance of the programmes for the MFF 2014-2020 in
    order to set out clear roles and responsibilities, and introduced increased planning, monitoring
    and reporting requirements. In line with this revised governance approach, each concerned
    Member State has appointed a Programme Coordinator (deputy minister or state secretary rank)
    to be responsible for the programming, coordination and monitoring of the decommissioning
    programme at national level. Currently the Programme Coordinators have to submit the annual
    work programmes for adoption by the Commission along with the relevant financing decision; in
    the next MFF the tools provided by the new Financial Regulation will be exploited and more
    analogies (to the extent possible) with the management and control structure for the cohesion
    policy funding will be sought in order to ensure streamlining and simplification.
    As far as programming is concerned the multiannual nature of the decommissioning programme
    will be reflected by the adoption of a multiannual work programme and financing decision, in
    line with the envisaged new financial regulation. This programming process will be evidently
    31
    synchronised with the evaluation steps (an interim one after four years, and a final one four years
    after 2027 to ensure completion of tasks in field).
    The Commission would entrust the implementation of the programmes' budget through pillar
    assessed implementing bodies (indirect management), i.e.:
    (i) in Bulgaria to the EBRD, with contributions to the Kozloduy International
    Decommissioning Support Fund;
    (ii) in Slovakia to the Slovak Innovation and Energy Agency (SIEA); the EBRD will
    mainly complete the implementation of projects already financed through the Bohunice
    International Decommissioning Support Fund.
    The establishment of a national agency in Bulgaria as implementing body of the Kozloduy
    programme should be assessed.
    Committees with monitoring and reporting functions are in place for each Member State, co-
    chaired by a Commission representative and the Programme Coordinators. Implementing bodies
    monitor on a day to day basis. In addition, the Commission services closely follow project
    implementation through desk and on-the-spot reviews on a biannual basis.
    As far as reporting is concerned, the practice of annual reporting to the European Parliament and
    the Council will be maintained.
    Presently the regular programming, monitoring and control cycle is supplemented by thematic
    verifications based on risk reviews. This practice has to continue in the next MFF.
    1.9.2. Performance indicators
    The present Regulation5
    has defined SMART specific objectives for the progress to be achieved
    in the funding period; those specific objectives have been further detailed with targets and
    indicators within the detailed implementation procedures12
    .
    Quite a number of output-based physical progress indicators are suitable both for defining
    specific objectives and for monitoring the performance (i.e. effectiveness) of decommissioning
    programmes; for example amounts of systems dismantled, materials released from regulatory
    control, radioactive waste processed, conditioned and stored or disposed of.
    Another important category of indicators is project-based; for example milestones i.e. significant
    events in a project properly budgeted and scheduled. Moreover, project management techniques
    such as critical path analysis and the EVM that provides robust project-based KPIs enabling the
    managers to control delays and cost-increases. Accordingly these indicators are used to assess the
    efficiency of the process.
    The combination of output-based and project-based indicators has proven to have a high potential
    for programmes such as nuclear decommissioning. Output-based indicators put very specific
    activities under the spotlight; the information they provide is sharp and clear, but also limited in
    that the full picture is not covered. Complementarily the EVM KPIs provide a complete view of
    the progress of individual projects/work packages and can be aggregated to inform on the general
    state of play of the overall programme, both time-wise and cost-wise.
    Such set of indicators (fully quantitative) enables control on short-term as well as on long-term
    issues, providing the managers (up to supervisory organisations) the tools to enact corrective or
    mitigation measures at the earliest time possible. This is a key feature for nuclear
    decommissioning programmes because the processes are not yet fully mature world-wide.
    The mid-term evaluation of the programmes has shown that this comprehensive toolkit of
    performance indicators has supported effective and efficient implementation as demonstrated by
    32
    the deeds, i.e. accomplishments. Therefore, the performance monitoring and evaluation for the
    future MFF can be profitably built on both the existing system and the lessons learnt to ensure
    continuous improvement.
    Under policy option 3 other indicators are needed to reflect safety related achievements in an
    even stricter manner and to match with the new explicit EU-wide knowledge sharing objective.
    Progressive and stepwise removal of radiological hazards posed by the facilities under
    decommissioning will have to be measured based on the safety cases prepared by the
    decommissioning license holder.
    As far as the EU-wide knowledge sharing objective is concerned, the following key items should
    be monitored without prejudice to the competitive advantage of the decommissioning license
    holders having created such know-how:
    (i) decommissioning cost estimations and estimations methodologies;
    (ii) radiation protection and industrial safety issues;
    (iii) identification of proven processes (e.g. decontamination of primary circuits).
    1.9.3. Preliminary evaluation criteria
    The Kozloduy programme and the Bohunice programme are expected to be completed
    respectively in 2030 and 2025. Thus the effectiveness and efficiency criteria for their evaluation
    are straightforward: achievement of the defined decommissioning end-state on schedule and on
    budget.
    Given the above, the current cycle of programme evaluations should be maintained, i.e. a mid-
    term and evaluation has to be scheduled as well as the mandatory final evaluation.
    1.10. JRC decommissioning and waste management programme
    1.10.1. Programming, monitoring and control system
    The D&WM programme is executed under the direct management mode and is governed by JRC
    senior management through a high level steering committee (chaired by the JRC Director-
    General)42
    . It meets three times per year to take strategic decisions, set up objectives and monitor
    the progress of the programme. The strategic decisions include e.g. the scheduling of shut-down
    of JRC nuclear facilities, taking due account to the infrastructure needs of the JRC Research and
    Training Work Programme.
    The high-level steering committee is supported by the operational-level steering committee,
    composed of site representatives of the D&WMP, and the responsible officers for legal, financial
    and procurement support of the D&WM programme. This committee meets three times per year,
    and aims to coordinate and monitor the D&WM programme activities at the different sites. It
    discusses technical, legal, financial and procurement issues of the D&WM programme and
    monitors both technical progress as well as budget implementation.
    42
    The D&WM high-level steering committee is composed of JRC Deputy Director-Generals as well as JRC
    Directorates currently affected by the D&WM programme (the Directorate for Nuclear Safety & Security,
    responsible for the implementation of the D&WMP; Directorate Strategy and Work Programme Coordination,
    and Directors responsible for Health & Safety, i.e. Site Directors in Ispra, Geel, Karlsruhe and Petten). Legal
    support is provided by the JRC unit for Legal Advice.
    33
    In line with the European Parliament resolution in 199943
    , the JRC is since the beginning of the
    D&WMP regularly advised by a group of independent European decommissioning experts
    (biannual meetings, and additional ad-hoc meetings), the D&WMP Expert Group. Their advice
    relates to the decommissioning and waste treatment strategy, the available technology, technical
    aspects of the organisation and any other aspects relating to the programme. Until 2016 experts
    were appointed by the Commission on the basis of proposals made by the Members of the JRC
    Board of Governors or by the JRC itself. In choosing these experts, the Commission took care to
    avoid any conflict of interest and to ensure independence of analysis and foster gender and
    geographical diversity. Following the new Commissions Decision on the creation of Commission
    Expert Groups44
    , the JRC has launched a new Call for Experts and established the Expert Group
    fully compliant to the new Commission rules.
    Since the beginning of the D&WMP, the Commission is regularly reporting to the Council and
    the European Parliament the progress and status of the D&MP, thereby providing an updated
    budget forecast (2004, 2008, and 2013)45
    .
    Moreover, JRC reports on an annual basis on the mid-term targets and the progress achieved
    (JRC Management Plan, JRC Annual Activity Report).46
    In the next financing period the multiannual nature of the decommissioning process will be
    reflected in the adoption of a multiannual work programme and financing decision, in line with
    the envisaged new financial regulation and taken into account the role of the JRC Board of
    Governors (article 4.2 of Commission Decision 96/282/Euratom on the reorganization of the
    Joint Research Centre). This programming process will be evidently synchronised with the
    evaluation steps (an interim one after four years, and a final one after 2027 when the completion
    of tasks in field is expected). Moreover, annual reporting to the European Parliament and the
    Council will be introduced in order to align and increase synergies between the programmes.
    1.10.2. Performance indicators
    The specific objectives defined in chapter 2.2.3 lay down the progress to be achieved in the next
    funding period. Progress has to be measured as appropriate by the establishment of appropriate
    and authorized pathways to implementation of decommissioning, by the quantity and type of
    safely stored or disposed of waste, by the quantity and type of safely stored or disposed of
    nuclear material and spent fuel, by the quantity and type of materials removed. The programme
    progress has to be generally measure also by earned value.
    43
    European Parliament resolution COM(1999) – 114 – C5-0214/1999 – 1999/2169(COS): "…ensure that the
    members of the committee of experts from the Member States that is to assist the JRC in its work are
    independent and properly qualified"
    44
    C(2016) 3301 final. COMMISSION DECISION of 30.5.2016 establishing horizontal rules on the creation and
    operation of Commission expert group
    45
    COM(1999)114, (COM(2004)621, COM(2008)903 and COM(2013)734).
    46
    Most recent publications: Management Plan 2017, 2016 Annual Activity Report
    34
    Annex 1: Procedural information
    1. LEAD DG(S), DECIDE PLANNING/CWP REFERENCES
    DG ENER, no entry in Decide Planning required
    2. ORGANISATION AND TIMING
    21 February 2018 – ISSG meeting
    18 April 2018 – ISSG meeting
    3. EVIDENCE, SOURCES AND QUALITY
    The following documents have been used as input to this ex-ante evaluation:
    [1] "Support to the mid-term evaluation of the Nuclear Decommissioning Assistance
    Programmes", EY, An evaluation for the European Commission DG Energy, 2018
    [2] "Report from the Commission to the European Parliament and the Council on the
    implementation of the work under the nuclear decommissioning assistance programme to
    Bulgaria, Lithuania and Slovakia in 2016 and previous years" of 20.06.2017 COM(2017)
    328 final
    [3] "Report from the Commission to the European Parliament and the Council on the
    implementation of the work under the nuclear decommissioning assistance programme to
    Bulgaria, Lithuania and Slovakia in 2015 and previous years" of 20.06.2016 COM(2016)
    405 final
    [4] "Report from the Commission to the European Parliament and the Council on the
    implementation of the work under the nuclear decommissioning assistance programme to
    Bulgaria, Lithuania and Slovakia in the period 2010-2014" of 03.03.2015 COM(2015) 78
    final
    [5] "Report on the assessment of the Nuclear Decommissioning Assistance Programme in
    view of the mid-term review of the financial framework 2014-2020"
    [Ares(2016)3562735]
    [6] "Nuclear Decommissioning Assistance Programme (NDAP) – Assessment of the
    robustness of the financing plans considering the economic-financial-budgetary situation
    in each concerned Member State and of the relevance and feasibility of the detailed
    decommissioning plans", Deloitte, NucAdvisor, VVA Europe, A study prepared for the
    European Commission DG Energy, 2016
    [7] ECA Special Report 22/2016 "EU nuclear decommissioning assistance programmes in
    Lithuania, Bulgaria and Slovakia: some progress made since 2011, but critical challenges
    ahead"
    35
    Annex 2: Funding
    Programme Planned end date
    Cost estimate
    [EUR million]
    Post-2020
    financing gap
    [EUR million]
    Kozloduy 2030 1 296 91
    Bohunice 2025 1 238 81
    JRC 2060 2 019
    Overall commitments until 2020 (EUR million)
    Programme < 2013 2014 – 2020 Total
    Kozloduy 850 293 1 143
    Bohunice 624 225 849
    Sub-Total 1 474 518 1 992
    JRC 330 205 535
    TOTAL 1 804 723 2 527
    Commitments for decommissioning activities until 2020 (EUR million)
    Programme < 2013 2014 – 2020 Total
    Kozloduy 491 293 784
    Bohunice 437 225 662
    Sub-Total 928 518 1 446
    JRC 330 205 535
    TOTAL 1 258 723 1 971
    EU contribution per year (average) (EUR million)
    Programme MFF 2014-2020 MFF 2021-2027 Δ%
    Kozloduy (BG) 41.9 9.0 -79%
    Bohunice (SK) 32.1 7.9 -76%
    Sub-Total NDAP 74.0 16.9 -77%
    JRC 29.3 49.7 +70%
    TOTAL 103.3 66.6 -36%
    Decommissioning average costs / year (EUR million)
    Programme MFF 2014-2020 MFF 2021-2027 Δ%
    Kozloduy (BG) 47.1 30.7 -35%
    Bohunice (SK) 107.3 35.6 -67%
    Sub-Total NDAP 154.4 66.3 -57%
    Sources: European Commission, Decommissioning plans, Monitoring reports, Mid-term
    evaluation study.